Attribution Services
Irlande – Services de conseil en ingénierie de la construction – Multi- Party Framework Agreement for HSE West Civil/Structural Engineering Services (C+S) - FW 05 Non Acute Healthcare Capital Works - Project Value €15M to €60M excl. Vat for HSE West
Avis publié en anglais. L'analyse IA vous le résume dans votre langue.
- Acheteur public
- Health Service Executive (HSE)
Kildare - Lieu d'exécution
- Kildare
- Valeur estimée
- 300 000 000 € HTVA
- Montant attribué
- 600 000 000 € HTVA
- Fin prévue du contrat
- 16 juin 2030
relance probable vers décembre 2029 - Offres reçues
- 11
- Forme
- Accord-cadre
Contrat de plusieurs années : l'acheteur passe commande au fil de ses besoins. - Procédure
- Procédure ouverte
Toute entreprise peut remettre une offre. - Publication
- 13 juillet 2026
- Langue de l'avis
- Anglais
Analyse IA : y aller ou pas ?
Résumé en français, critères, documents à fournir et verdict GO / NO GO en une minute.
Analyses illimitées pendant les 14 jours d'essai Pro, sans carte.
Description
Multi- Party Framework Agreement for HSE West Civil / Structural Engineering Services (C+S) Framework 2025 - Framework 05 Non Acute Healthcare Capital Works - Project Value €15M to €60M excl. Vat for HSE West region (Galway, Mayo and Roscommon). The Initial project will consist of the construction of a new build 75 bed Community Nursing unit (CNU) within the Ballina District Hospital campus with direct linkages into the existing Ballina District Hospital.
The new build 75 bed Community Nursing unit (CNU) will consist of 3 floors with 25 single ensuite bed room accommodation to HIQA standards for Residential Care Settings for Older People in Ireland at each level Ground Floor, First Floor, Second Floor (level 0,1, 2) along with linkages to existing hospital street, new stairways, service lift and new 2 Nr. Bed Lifts, including new carpark areas, etc. Note: on the Ground Floor there will be 10 single ensuite bedrooms which will be allocated to residents with dementia.
There will also be extensive re-planning, upgrade works and reconfiguration of the existing district hospital female wing including physiotherapy area within the single storey and the two-storey central building structure, to provide commercial production kitchen with ancillary support rooms, physiotherapy area, laundry, staff changing and Day-care Services, etc; to complete the interface works with new the 75-bed CNU unit on site. The floor area of this project is in the region of 7,960 m2 which consists of the following: Demolishing the existing building structure on site, Construction and fit-out of a new 75 bed Community Nursing unit over 3 floors and roof top M E Plant room include extensive garden areas for the CNU, Refurbishment of the Existing Main District Hospital, Construction of new Car parking areas on site, Construction of a new Sub-station building including generator room and the Construction of a new medical building. Each element of building works, Demolishing, Diversion of Underground Services, construction of the new 75 bed CNU, etc, will be tendered as a separate construction contracts (such as enabling works packages main construction package), subject to statutory approvals, HSE Approvals, Funding etc., Please see SAQ document pack.
Attribué à
Codes CPV
Codes européens qui classent l'objet du marché. C'est grâce à eux que nous retrouvons les marchés de votre métier.
71312000 71311000
Prix gagnants des marchés comparables
- Un quart sous
- 68 984 €
- Médiane
- 300 000 €
- Un quart au-dessus de
- 1 000 000 €
Montants HTVA attribués ces 3 dernières années pour 37 marchés du même groupe CPV (7131…), hors accords-cadres. La moitié des marchés se situe entre les deux quartiles. Source TED : surtout des marchés au-dessus des seuils européens, donc des montants plutôt élevés.
Marchés similaires déjà attribués
Source : TED – Office des publications de l'Union européenne © Union européenne, données retraitées. Référence 479802-2026.