Award notice Works
Durchführung von Baumeisterarbeiten Umspannwerk Spannberg
Notice published in German. The AI analysis summarises it for you in your language.
- Public buyer
- Netz Niederösterreich GmbH
Maria Enzersdorf - Place of performance
- Maria Enzersdorf
- Amount awarded
- €6,136,975 excl. VAT
- Planned end of contract
- 31 May 2028
likely re-tender around December 2027 - Bids received
- 5
- Procedure
- Competitive negotiated procedure
You first submit an application; shortlisted candidates bid, then negotiate with the buyer. - Publication
- 16 July 2026
- Notice language
- German
AI analysis: go for it or not?
Summary in English, criteria, documents to provide and a GO / NO GO verdict in one minute.
Unlimited analyses during the 14-day Pro trial, no card needed.
Description
Errichtung eines neuen Umspannwerkes in Spannberg sowie Umbau-arbeiten in der Bestandanlage. Bestehend aus einem Betriebsgebäu-de, Acht Umspanner-Fundamenten, zwei EB-Fundamenten, sechs Abspannportalen und über 500 Gerätetischfundamenten. Das Bau-feld ist, aufgrund der Höhenunterschiede, aufzuschütten
Awarded to
CPV codes
European codes that classify what the contract is about. They are how we find the tenders for your trade.
45220000
Winning prices for comparable contracts
- A quarter below
- €6,136,975
- Median
- €8,769,967
- A quarter above
- €11,867,445
Amounts awarded (excl. VAT) over the last 3 years for 5 contracts in the same CPV group (4522…), excluding framework agreements. Half of the contracts fall between the two quartiles. TED source: mostly contracts above the EU thresholds, so amounts tend to be high.
Similar contracts already awarded
| Contract | Winner | Amount |
|---|---|---|
| Stahlbauarbeiten U-Bahn-Linie U2 Bauabschnitt U2/17 „TVM-Vortriebe“, U2/19 „Reinprechtsdorfer Straße“, U2/20„Pilgramgasse“, U2/21 „Neubaugasse“ und U2/22 „Rathaus“ WIENER LINIEN GmbH & Co KG · 10 August 2026 |
Kovoreal - Holic s.r.o. Strabag AG Rudolf Metallbau GmbH |
€87,301,424 |
| L 191, Frastanz – Feldkirch, Stadttunnel Feldkirch, L 191, Tisner Straße, km 2,510 – km 2,761, Umlegung Portal Tisis mit Radweg und Anbindung L 191a Land Vorarlberg · 31 July 2026 |
HTB Baugesellschaft mbH | €11,867,445 |
| KDO-SPN - Bauschlosser Stadt Wien - Wiener Gesundheitsverbund · 22 July 2026 |
m + e metallbau gmbh | €332,785 |
| B1960 Klosterneuburger Hochstraße - GU Bau Magistrat der Stadt Wien - Magistratsabteilung 29 · 20 July 2026 |
HABAU Hoch- und Tiefbaugesellschaft m.b.H. | €8,769,967 |
Source : TED – Office des publications de l'Union européenne © Union européenne, données retraitées. Reference 491980-2026.